Search
EN
Free Quote

How To Build A Double Girder Overhead Crane?​

News

A double girder overhead crane is a kind of heavy lifting equipment widely used in factories, warehouses, harbors, and other places. It consists of two parallel main girders, end girders, lifting trolleys, and an electrical control system. Compared with the single girder structure, it has a higher load carrying capacity (usually 5~550 tons), and the structure and installation process are more complicated, usually requiring strict technical requirements. In this article, we will introduce the installation process of how to build a double girder overhead crane in detail by combining the industry standard and actual engineering experience. Please continue reading below.

Step I: Pre-Construction Preparation

The installation of a double girder overhead crane is a systematic project, covering mechanical, electrical, civil construction, and other specialized fields. Before formal installation, sufficient preparation work must be done, mainly including the following:

1. On-Site Investigation And Development Of Construction Programs

  • Confirmation of basic parameters: detailed verification of the design drawings and the actual working conditions on site, confirming the span, lifting height, column bearing capacity, and other key parameters.
  • Technical documents: Prepare the general assembly diagram, electrical schematic diagram, installation manual, and quality certification documents.
  • Formulation of construction program: including lifting process, safety measures, and emergency plans.

2. Inventory materials and prepare installation tools

  • Inventory the main components, such as main beams, end beams, traveling mechanism, etc., according to the packing list.
  • Prepare special lifting equipment and installation tools: lifting equipment such as an automobile crane, a gantry crane, etc. Installation tools include a laser level meter (accuracy 0.02mm/m), a latitude and longitude meter, a hydraulic torque wrench (range 1000N-m), and welding equipment.
  • In addition, please pay attention to equip safety protection facilities, set up a warning area, wear a helmet, safety belt, fall arrester, safety rope, and other equipment for working at height.

Step II: Track Installation

Double-beam bridge cranes usually use QU-type or P-type tracks. The installation accuracy directly affects the equipment's running stability and wheel rim wear.

1. Track installation standards

  • Before installing the track, it is necessary to conduct a basic acceptance, including testing the track beam concrete strength (≥C30), measuring the position deviation of the embedded parts (≤5mm), and checking the flatness of the track pad (≤1mm/m).

2. Installation requirements:

Track straightness error ≤1mm/m, total length ≤5mm, track joint gap 2~4mm, height difference ≤1mm, track horizontal deviation ≤1/1000, span deviation ±5mm.

3. Track fixing method

  • Press plate fixing: Use high-strength bolts to fix the track, with a spacing of ≤600mm.
  • Welding fixation (optional): Suitable for heavy cranes, a low-stress welding process is required.

4. Track electrical safety

  • Grounding treatment: Both ends of the track are reliably grounded, and the grounding resistance is ≤4Ω.
  • Anti-collision buffer: Stoppers are installed at the ends of the track to prevent the crane from derailing.

Step III. Assembly and hoisting of the main structure of the crane

The main beam and end beam of the double-beam overhead crane are usually transported separately and need to be assembled on site.

1. End beam assembly

  • Assemble the end beam on a flat ground and adjust the parallelism of the wheels (deviation ≤ L/1000, L is the measured length).
  • Use a torque wrench to tighten the high-strength bolts according to the standard (such as an M20 bolt torque is about 400N·m).

2. Main beam hoisting

  • Single beam hoisting method: Lift the main girder on one side first, adjust the level and fix it, then lift the other side.
  • Integral hoisting method (applicable to a small double-beam overhead crane): complete the connection between the main beam and the end beam on the ground and hoist as a whole.
  • Precautions for hoisting: Use a balance beam to avoid deformation of the main beam. And install temporary supports immediately after hoisting to prevent overturning.

3. Connection between the main beam and the end beam

  • Use high-strength bolts to connect, and tighten in the order of initial tightening (30% torque) → final tightening (100% torque) → re-tightening.
  • Check the camber of the main beam (usually S/1000, S is the span) to ensure that it meets the design requirements.

Step Ⅳ. Electrical system installation and commissioning

1. Safe busbar installation

  • The busbar straightness error is ≤±2mm/m, and the collector has good contact.
  • The three-phase insulation resistance is ≥1MΩ to avoid short circuit risks.

2. Control cabinet and motor commissioning

  • Wire according to the electrical drawings to ensure that each limit switch (hoisting, trolley, and car) is sensitive.
  • Adjust the brake clearance (0.5~0.8mm) and test the brake slippage (≤S/100).

Step V. Machine commissioning and acceptance

1. No-load test

  • The trolley and car run 3 times throughout the whole process to check for jamming and abnormal noise.
  • The hoisting mechanism rises and falls throughout the whole process to test the reliability of the limit switch.

2. Static load test

  • Load 1.25 times the rated load, hover for 10 minutes, and check the deflection of the main beam (≤S/800).
  • Check for permanent deformation after unloading (≤S/1000).

3. Dynamic load test

  • Load 1.1 times the rated load and perform compound actions (lifting + trolley/trolley operation).
  • Test the braking performance to ensure that there is no abnormal vibration.

4. Acceptance documents

Installation record, commissioning report, special equipment inspection certificate (issued by the local quality inspection department).

Step Ⅶ. Double-Girder Overhead Cranes Safety Operation & Maintenance Recommendations

CategoryItemTechnical Requirements
Daily InspectionWire Rope InspectionBroken wires ≤10% of total wires
Wheel Flange WearWear ≤30% of original thickness
Bolt TightnessVerify the insulation performance of electrical circuits
Electrical InsulationLubricate bearings, gears, and wire ropes
Periodic MaintenanceMonthly Maintenance1. Check rail fastening condition
2. Adjust the brake system
Quarterly Maintenance1. Comprehensive inspection
2. Conduct a load test if necessary
Annual MaintenanceOperators must hold a valid certification
Operator TrainingCertification RequirementOperators must hold valid certification
Equipment FamiliarizationMust understand equipment parameters and emergency procedures
Prohibited Operations1. No overloading
2. No diagonal pulling
3. No emergency stopping

Conclusion

The above is a detailed guide on how to build a double girder overhead crane, following the construction in strict accordance with the specifications. It is recommended to choose a professional team with special equipment installation qualifications for installation and regular maintenance to ensure safe production. Weihua, as a famous overhead crane manufacturer and factory in China, provides a one-stop lifting solution and installation service. For technical support or on-site installation service, you can choose to contact our professional team.

Recent News

How Can We Help ?

Speak with a human to filling out a form? We will connect you with a team member who can help.
Contact Now

Hot Products

Email

[email protected]

𐀟

Message

Whatsapp

+8615803735886

Submit Request

en_USEN